67

 

At a Crematorium in Berkshire. The 20 tonne cremator was off loaded using a 200 ton crane, lowered down onto a raised platform (railway sleepers, steel plates), Skated in positon using jaks, skates, winch, etc, when in position, lined, levelled and fastened down, we then installed the remainder of the Abatement Plant, (boiler, ductwork, filter unit, etc), again lined, levelled and fastened down where necessary.

04.12.12