20141127_120459Hanlon and Wright recently completed the install of a 22 ton cremator along with the abatement plant, The cremator was off loaded from incoming transport using a 200 ton crane, which lowered it onto a prepared platform at the door enrance.

The cremator was then winched into position, lined, levelled and fastened down.

The abatement plant was then lifted into position using a compact mini crane and bolted together, lined and levelled.

20141127_105745