Prior to lifting the old column out, we collected the new column from premises in Wrexham using one of our extendable trailers and delivered to site. We then unbolted the base and using an 160ton crane lifted the old column out, then laying over using one of our hi-ab type cranes to tail the column. Using the same hi-ab type crane and 160ton mobile crane the new column was lifted into the vertical position then uplifted and lowered into position within the steel structure, once in postion we bolted the column back to the base.

15.03.13