Tel:0161 330 7631 Email: enquiries@hanlonandwright.co.uk

78

Using 2 x 5 ton adjustable gantries along with 4 x chain blocks, we disconnected the electrics, air, water, etc, and unbolted from it's base, the compressor was then uplifted and carefully moved to one side and lowered onto a specially made pallet, and secured. We then skated the compressor through the plant room to the entrance and loaded onto our transport using the hi-ab type crane, secured, sheeted and then delivered to premises in France whilst work was carried out on the compressor.

23.03.13